~4 hour check out flight of the GV with LVIS and DMS installed was completed today.
Both LVIS and DMS operated with no issues. Three of the 4 IMU’s worked well, however the 4th unit did not operate and will be investigated before the next flight.
The LVIS system collected good alignment data over the desert, numerous roll and pitch calibration maneuvers over water, and multiple passes over the ramp (ground GPS survey) at Broomfield. DMS also successfully collected data throughout the flight as well as during the calibration passes over the Broomfield ramp.
OIB Fall 2015
Submitted by
John Woods on 09/11/15
Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.